Loop 88 Opened in April. Both Ends of It Are Still Years From Done.

On April 16, 2026, state and city leaders cut the ribbon on four miles of six-lane freeway along 130th Street. That afternoon, crews started pulling barriers off the on-ramps. Five months later, on Sept. 9, a different contractor was scheduled to start tearing up the pavement at the freeway's east end. That project is expected to run until fall 2031.

The new Loop 88 is a finished middle. At its east end, the I-27 interchange is in the early months of a five-year rebuild. At its west end, the next stretch exists only as a planning estimate. If you drive 130th Street every day, you'll be living with construction at one end or the other well past the opening.

The Middle Four Miles Are the Part That's Done

TxDOT calls the opened section Phases 3A and 3B. It rebuilt FM 1585, the road most of South Lubbock calls 130th Street, from Avenue U to Chicago Avenue. What used to be a two-lane rural road is now a six-lane freeway with frontage roads, bridges and ramps. When TxDOT broke ground in 2021, it split the job at Memphis Avenue. 3A ran from Avenue U to Memphis, and 3B continued from Memphis to Chicago. From groundbreaking to ribbon-cutting took about four and a half years.

At the opening, Mayor Mark McBrayer compared the new loop to Loop 289. He said people once could hardly believe anything would be built outside that loop, "but now we're all the way out here," according to KCBD's coverage of the opening.

Those four miles are a small slice of the whole plan. TxDOT describes Loop 88 as about 12.4 miles of road west of US 84. The plan is to turn two-lane rural roads into an access-controlled, six-lane divided freeway with frontage roads and ramps. Even within Segment 3, which runs from US 87 to US 62/82 in Wolfforth, KCBD's September release counts seven phases bundled into five projects. 3C is only the third. TxDOT's own Phase 3C page still lists Sections 3D, 3E and 3F/3G as the remaining work.

The East End Is a Five-Year Job That Started in September

Phase 3C picks up exactly where the opened freeway stops. Its limits run from Avenue U to half a mile east of I-27/US 87. They also cover the I-27 corridor itself between 114th and 146th Streets. TxDOT puts the price at $221.6 million. Williams Brothers Construction Co., Inc., of Houston was scheduled to begin on Wednesday, Sept. 9, 2026. Completion is expected in fall 2031.

Put that against 3A and 3B. The opened section took four miles and about four and a half years. 3C covers less ground but has a longer calendar ahead of it, because it rebuilds the place where Lubbock's two loops meet the interstate. Counting from the week this post goes up, fall 2031 is almost five years away. A first-grader at the Avenue U light this fall could be finishing middle school by then.

The sequence matters for how the drive will feel over those years. Joe Villalobos, P.E., TxDOT Lubbock Area Engineer, laid out the order in the news release KCBD published Sept. 3:

"Traffic will continue to be one-lane in each direction as work to construct the frontage roads begins. As construction ramps up, plans include reduced speed limits in the project limits on both FM 1585 and I-27/US 87. Drivers can also expect traffic changes along the interstate when work to rebuild the I-27, Loop 88 interchange begins."

That's from KCBD's report on the Phase 3C start. Frontage roads come first, then lower speed limits as the work grows, then changes on I-27 itself once the interchange rebuild starts. The stretch that looks finished from Avenue U westward ends where the slowest part of the corridor begins.

What Changed at Avenues U and P

The first visible change came a few weeks after crews mobilized. TxDOT announced that Avenues U and P would become all-way stops on Wednesday, Oct. 7, weather permitting, with message boards posted ahead of the switch. Villalobos explained the reason in the same release. Before the change, northbound Avenue U traffic had no access to westbound FM 1585. Connecting Avenue U directly to the road and putting all-way stops at both intersections was meant to keep traffic moving while crews started on the frontage road.

The announced plan has three pieces:

  1. Restripe FM 1585 between Avenue P and Avenue U so that segment carries two-way traffic again.
  2. Remove the eastbound pavement between P and U.
  3. Reopen the Avenue U crossover.

For anyone heading north on Avenue U, that makes two stops instead of one. You stop first at the eastbound frontage road and again at the north end of the crossover, then turn onto either westbound or eastbound FM 1585. EverythingLubbock carried the same notice on Oct. 2.

This is a small change with a long tail. Avenues U and P sit right at the hinge between the open freeway and the 3C work zone. Their traffic pattern will keep shifting as the frontage roads go in and the interchange work moves toward I-27.

The West End Has a Planning Window, Not a Start Date

Past Chicago Avenue, the freeway ends again. TxDOT's segment map puts the remaining Segment 3 sections west of Chicago, toward Milwaukee Avenue, Upland Avenue and Wolfforth.

Two FM 1585 projects heading west from where the opened freeway stops appear in TxDOT's 2027 Unified Transportation Program, which the Texas Transportation Commission adopted on Aug. 26, 2026:

FM 1585 stretch TxDOT project number Estimated letting Estimated cost
Quincy Avenue to Chicago Avenue 1502-01-032 FY 2027–2030 $153.3 million
0.5 mile east of FM 179 to Quincy Avenue 1502-01-034 FY 2031–2036 $95.4 million

"Letting" is when TxDOT puts a contract out to bid. Construction starts after that. The UTP gives each project a window of several fiscal years rather than a date. Even at the early end, the next stretch west of Chicago would go to bid no sooner than fiscal 2027. At the late end, bidding could still be underway in fiscal 2030, close to when 3C is scheduled to wrap up in fall 2031.

Each piece also takes years to build once it starts. On 3A and 3B, about four and a half years passed between groundbreaking and opening, and 3C is scheduled to run about five. So the two ends of the opened freeway are likely to be work zones at the same time for part of the next several years, one at I-27 and one west of Chicago.

How This Shapes a South Lubbock Commute Through 2031

For a household along the 130th Street corridor, this sets the calendar for the rest of the decade.

  • Between Avenue U and Chicago Avenue, the freeway, frontage roads and ramps are open and finished. That's the one part of Segment 3 where the road you drive now is the road you'll drive in 2031.
  • From Avenue U east to I-27, expect one lane each way while the frontage roads go in. TxDOT plans lower speed limits on both FM 1585 and I-27 as the work ramps up, and traffic changes on the interstate once the interchange rebuild begins, all on a schedule that runs to fall 2031.
  • I-27 between 114th and 146th Streets is inside the 3C limits too. If your usual route skips 130th Street and stays on the interstate, it still passes through the project.
  • West of Chicago Avenue, the road stays as it is until the Quincy-to-Chicago project goes to bid, which the UTP places somewhere in FY 2027–2030.

TxDOT's standing advice for the 3C zone is to watch for slow construction equipment, follow posted speed limits, expect delays and use alternate routes around the work when possible. The best source for the next traffic switch is TxDOT's Loop 88 Segment 3C project page. The next lane change near I-27 will be announced there and in the local releases that follow it.

Both the mayor and Lubbock County Judge Curtis Parrish described Loop 88 at the opening as the foundation for future growth. Parrish said highways like this "generate growth," as KCBD reported. On the ground in South Lubbock, that growth will arrive over five years of construction at the I-27 end, with a bid window still open at the Chicago end.

If you own a home near 130th Street and want to know how the corridor's timeline fits your home's value now, the team at Panhandle Realty Group follows these projects closely and can walk you through it. Start with your instant home valuation, then talk with a local agent who drives Loop 88 too.

Work With Us

Get assistance in determining current property value, crafting a competitive offer, writing and negotiating a contract, and much more. Contact us today.

Follow Me on Instagram